BUS 204 Project Management -  Final Test
Reference: Project Management Achieving Competitive Advantage. 3rd edition. Jeffrey K. Pinto



1.Imagine you are a project team member on a project that has been missing deadlines, not producing the technological results hoped for, and is a source of problems between your team and the customer.  You have just been informed that the project is being cancelled?  In what ways is this good news and how would you view it as bad news?






2.Using the following data, calculate the planned and actual monthly budgets through the end of June.  Assume the project is planned for a 12-month duration and $250,000 budget.  



Activity		Jan	Feb	Mar	Apr	May	Jun	Plan	% C	Value

Staffing		8	7					15	100		

Blueprinting			4	6				10	100 		

Prototype
   Development			2	8			10	70 		

Full Design					3	8	10	21	67 		

Construction						2	30	32	25 		

Transfer							10	10	0 		


Monthly Plan											
Cumulative											
Monthly Actual 	10	15	6	14	9	40	
Cumul. Actual											


3.What do the schedule performance index and budget performance index demonstrate?  How can a project manager use this information to estimate future project performance? 







4.  Comment on the different methods for project termination.  How have you seen an example of one of these methods, through either your school or work experience?




























5) Compute early and late start and finish times for the network shown.



 

Early and late start and finish times are given in the table.

Task	Early Start	Early Finish	Late  Start	Late Finish
A	0	6	0	6
B	6	11	16	21
C	18	27	21	30
D	6	10	14	18
E	18	30	18	30
F	6	18	6	18
G	30	38	30	38

				














6) Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other path be watched and why?
 
Activity	Predecessor	Optimistic	Likely	Pessimistic
A	--	4	6	10
B	A	2	5	8
C	A	6	7	9
D	B	3	9	20
E	C	7	9	11
F	D,E	7	11	19
				









7) A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?

 

Resource 
Number	Daily Rate
1	$1,000
2	$1,200
3	$500
4	$750
5	$800

Activity	Length	Activity	Length
H	3	S	3
M	9	J	1
P	6	W	4
B	7	T	4
R	9	G	4
F	5	K	10













8) What is the student syndrome and what makes it a useful model for highlighting common project efforts?















9) Create a resource loading table and perform resource leveling on the project composed of the activities in this table. Activities listed in the table are measured in the number of eight-hour days. The maximum amount of time used per day is 16 hours.
 
Activity	Time	Predecessor
A	6	--
B	1	--
C	2	A, B
D	4	--
E	1	C, D
F	1	E
G	6	E
H	4	F
J	4	F
K	3	G, H
L	5	J, K
M	3	L





























10) Identify a different key success driver and inhibitor for the project stages of formation, build-up, main phase, and close-out.












11) Sketch the Seven Elements of Project Closeout Management model and discuss what takes place at each step.

Finishing the work —
Handing over the product —
Gaining acceptance for the product —
Harvesting the benefits —
Reviewing how it all went —
Putting it all to bed —
Disbanding the team — 







Calculate Your Essay Price
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Order your essay today and save 10% with the coupon code: best10