Wk6 | Management homework help
You are a project manager on a project that uses earned value management. The project has the following budget and status: Project Duration (months): 14 Current Reporting Period (month): 6 BAC: $387,000 Cumulative PV: $68,345 Cumulative AC: $78,379 % of the project completed through the reporting period: 19% Estimate to Complete: $294,677 Based on this information, determine the following: Cumulative EV Schedule Variance (SV) Schedule […]